Tender Evaluation and How to File an Objection (Sanggah) and Appeal (Sanggah Banding), 2026 Rules

How the selection committee (Pokja) evaluates Indonesian government construction bids: administrative, technical, price and qualification checks, arithmetic correction, unbalanced unit prices, the price check below 80% of the owner’s estimate, and how and when to file an objection and appeal under Perpres 46/2025 and LKPP Regulation 3/2026.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Many bids fail not on price but on documents. Knowing the evaluation order helps prepare a bid that passes, and if you lose for the wrong reason, when and how to object.

Open bidsAdministrativeTechnicalPriceQualificationAward, objection
Evaluation order in a post-qualification tender.

How bids are evaluated

Example: HPS Rp1.2 bn

SituationResult
Corrected bid Rp936 m (78% of HPS)Price reasonableness check; have unit price analyses ready
If found reasonablePerformance guarantee Rp60 m (5% of HPS), not Rp46.8 m (5% of the bid)
Unit price Rp1,150,000 against an HPS of Rp1,000,000115%: likely treated as unbalanced and clarified
Filing an appealAppeal guarantee Rp12 m (1% of HPS)

Objection and appeal

StepDeadlineNote
Objection (sanggah)Filed through SPSE within 5 calendar days of the award announcement, ending on a working day and hourThe Pokja answers within 3 calendar days after the objection period ends
Appeal (sanggah banding)As scheduled in SPSE and the tender documentsOnly for construction and integrated work; with an appeal guarantee of 1% of HPS; answered by the budget authority (KPA); stops the tender
KPA answerWithin 14 calendar days of receiving confirmation of the appeal guarantee (LKPP Regulation 3/2026)The old rule said 14 working days

Legal basis for government projects: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (set in September 2026, replacing LKPP Regulation 12/2021). Tenders started before the new rule and contracts already signed still follow the old rule and their contract terms. The new rule also focuses on bidders’ beneficial owners, collusion and "borrowed flag" bidding. Electronic guarantees with a valid e-signature and e-stamp no longer need a paper original. Always check the SPSE schedule and your package’s tender documents, because those are binding.

Common reasons bids fail

Common mistakes when objecting

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

How long is the objection period?

Five calendar days after the award announcement, ending on a working day and hour, filed through SPSE. The exact dates are in the tender schedule in SPSE.

How large is the appeal guarantee?

One percent of the owner’s estimate (HPS), and appeals apply only to construction and integrated work.

What happens to a bid below 80% of HPS?

The Pokja checks whether the price is reasonable. If not, the bid is rejected; if so, the performance guarantee becomes 5% of HPS.