Guarantees on Construction Projects: Bid, Performance, Down Payment and Maintenance

The five kinds of construction project guarantee, their usual amounts, when they are given and returned, their forms (bank guarantee or surety bond), and how to include their cost in the tender and cash flow.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

A guarantee is a promise from a bank or insurer to the client that the contractor will meet its obligations. If the contractor fails, the client can call the guarantee. On Indonesian government procurement, guarantees can be bank guarantees or surety bonds (Perpres 46/2025 Article 30).

123456789101112Bid guaranteePerformance guaranteeDown payment guaranteeMaintenance guaranteeMonth
When each guarantee runs, for an 8-month project with a maintenance period.

Kinds of guarantee and their amounts

GuaranteeWhat it coversUsual amountRuns until
BidThe bidder does not withdraw after winningAs the tender documents say, often 1% to 3% of the HPSThe contract is signed
Appeal (sanggah banding)When a bidder files an appealAs the tender documents sayThe appeal is decided
PerformanceThe work is completed as contracted5% of the contract; 5% of the HPS if the offer is below 80% of itFirst handover (PHO)
Down paymentThe down payment is repaid through payment deductionsThe down payment amountThe down payment is fully deducted
MaintenanceDefects are fixed during the maintenance period5% of the contract, replacing retentionFinal handover (FHO)

For a Rp1 billion contract with a 20% down payment: a Rp50 m performance guarantee, a Rp200 m down payment guarantee and a Rp50 m maintenance guarantee. The 5% retention can be replaced by a maintenance guarantee, so payments are made in full (Perpres 16/2018 Article 53).

Guarantee costs and cash flow

Common mistakes

Start from a template

The full guide is in How to create a construction finance report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What kinds of construction guarantee are there?

Bid, appeal, performance, down payment and maintenance guarantees, as bank guarantees or surety bonds.

How large is the performance guarantee?

Usually 5% of the contract value; on government tenders 5% of the HPS if the offer is below 80% of it.

How does retention differ from a maintenance guarantee?

Retention is part of a payment held back; a maintenance guarantee replaces it with a bank or insurance guarantee, so the payment is received in full.

References

  1. BPK Central Sulawesi: guarantees in government procurement (Indonesian): kinds and amounts
  2. Hukumonline: retention and maintenance guarantees (Indonesian): 5% retention, Article 53