1 · PreconstructionCost control / PRACTICAL GUIDE

Unit Price Analysis (AHSP) for Construction: How to Calculate It, with an Example

How to calculate a construction unit price analysis (AHSP): material and labour coefficients, base prices, overhead, and a worked example for the budget.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

A unit price analysis (AHSP, Analisa Harga Satuan Pekerjaan) explains where a unit price in the budget comes from: how much material and labour one unit of work needs, multiplied by their prices. With it, unit prices can be checked and updated when material prices rise.

Example: 1 m2 of 7.5 cm lightweight block (hebel) wall

ComponentCoefficientBase priceAmount
Lightweight block 7.5 × 20 × 60 cm8.4 piecesRp3,900Rp32,760
Block adhesive (thin-bed mortar)3 kgRp1,200Rp3,600
Laying labour (piece rate)1 m2Rp13,000Rp13,000
Material + labourRp49,360
Overhead and profit 10%Rp4,936
Unit price per m2Rp54,296

These are example 2026 market prices from housing project purchases, rounded. 7.5 cm blocks are usually bought per m3, at about Rp390,000 to Rp490,000 including VAT. One m3 holds about 111 blocks (1 ÷ (0.6 × 0.2 × 0.075)), so about Rp3,900 a block. One m2 of wall needs 8.33 blocks (1 ÷ (0.6 × 0.2)); 8.4 allows a little for offcuts. Adhesive use is usually 2.5 to 4 kg per m2 for a 3 mm joint; this example uses 3 kg. Adhesive comes in 40 kg bags at about Rp45,000 to Rp50,000.

In this example the crew is paid a piece rate per m2. When labour is paid by the day, it is worked out in man-days (OH, orang hari): for example 0.1 man-day of a skilled worker × Rp150,000 plus 0.2 man-day of a labourer × Rp120,000, which is Rp39,000 per m2. Official coefficients are usually higher because they include a head mason and a foreman; see the next section. Compare them with your piece rate: a big gap needs checking.

The official AHSP layout

For government work in Indonesia, the AHSP follows Permen PUPR No. 8 of 2023 (which replaced Permen PUPR 1/2022), with coefficient tables updated by circulars from the Directorate General of Construction. The layout:

RowContents
A. LabourLabourer, mason, head mason, foreman (in man-days)
B. MaterialsMaterials per unit of work
C. EquipmentTools, if any
D. TotalA + B + C
E. Overhead and profit10% to 15% of D
F. Unit priceD + E

Widely quoted labour coefficients for 1 m2 of 7.5 cm lightweight block wall (2016 AHSP): labourer 0.35, mason 0.13, head mason 0.013, foreman 0.003 man-days. At Rp120,000, Rp150,000, Rp170,000 and Rp180,000 a day, labour comes to about Rp64,250 per m2. Check the current official table. On government budgets, construction safety cost (SMKK) and VAT are added in the summary, not in the AHSP.

How to build an AHSP

  1. Choose the unit of work: m2, m3, m1, piece or lump sum.
  2. List the materials and labour for one unit, with their coefficients.
  3. Fill in current base prices and daily wages at the project location.
  4. Multiply each coefficient by its base price and add them up.
  5. Add overhead and profit (10% to 15% on government work), and use the result as the unit price in the budget.
Swipe sideways to see every column →
The RAB Material tab in the free template
The RAB Material tab in the free template: the unit price from the AHSP goes in the unit price column and is multiplied by the quantity.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is an AHSP?

Analisa Harga Satuan Pekerjaan, a unit price analysis: the price of one unit of work from the material and labour it needs times their base prices, plus overhead and profit.

What is a coefficient in an AHSP?

How much material or labour one unit of work needs, for example 8.4 lightweight blocks per m2 of wall.

How does the AHSP relate to the budget (RAB)?

The AHSP gives the unit price; the budget multiplies that unit price by each work item’s quantity.

What does OH mean?

Orang hari, a man-day: the unit of labour. 0.2 man-day of a labourer is one labourer for a fifth of a day.

References

  1. Permen PUPR No. 8 of 2023 (JDIH PUPR, Indonesian): the AHSP regulation in force
  2. BPK regulations database: Permen PUPR 8/2023 (Indonesian): in force, and what it revoked