How to Prepare a Construction Tender Offer and Bid Summary

How to build a tender price from your cost plan (RAP): head office overhead, risk allowance and profit, what the offer letter contains, the bid summary, and how to check the price against the owner’s estimate (HPS).

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

The winning price is not the cheapest one, but the cheapest one that still makes money. So the tender price is built from the bottom up: start from the RAP (your real cost), then add head office overhead, a risk allowance and profit.

85%8%
  • RAP project cost Rp850 m
  • Head office overhead Rp40 m
  • Risk allowance Rp25 m
  • Profit Rp85 m
How a Rp1,000 m tender price is built, before VAT · VAT is added on top.

Steps for building the tender price

  1. Take quantities off the drawings and specification (BOQ), or check the client’s BOQ.
  2. Build the RAP: real supplier prices, labour-contract rates and your crew’s productivity, plus site overhead.
  3. Add head office overhead (this project’s share of office costs), a risk allowance and profit.
  4. Spread those additions over each item’s unit price, because the offer is priced per item, not per component.
  5. Add up, add VAT, round, and fill in the bid summary.
  6. Compare with the owner’s estimate (HPS) if it is known.

The offer letter and its attachments

DocumentContents
Offer letterPackage name, total price in figures and words, offer validity, completion period, signature and stamp
Bid summaryTotal per section of work, VAT, grand total, rounded
Priced bill of quantitiesEvery item: code, description, unit, quantity, unit price, amount
Unit price analysisIf requested, especially for the main items
Programme and method statementPlanned S-curve and the order of work
Bid guaranteeIf the tender documents require one

Checking the price is reasonable

Swipe sideways to see every column →
The tab in the free template used for this work, with fictional example rows.
The tab in the free template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

How do I work out a tender price?

Start from the RAP (real cost), add head office overhead, a risk allowance and profit, spread them over each item’s unit price, then add VAT.

What is a bid summary?

The total price per section of work, plus VAT, giving the offer total.

What happens if the offer is below 80% of the HPS?

On government tenders it is clarified for reasonableness, and the performance guarantee is based on the HPS.

References

  1. BPK Central Sulawesi: guarantees in government procurement (Indonesian): performance guarantee based on the HPS below 80%