Construction Tender Qualification Checklist: How Not to Be Rejected (2026 Rules)

A checklist for qualification in Indonesian government construction tenders: SBU, managerial staff SKK, experience, remaining package capacity (SKP), basic capability (KD), equipment, KSWP, bid security, borrowed-name bidding, and the rejection reasons recorded in official evaluation reports.

Komander.ai Panduan team · 4 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Official tender evaluation reports show the same pattern: bids fail because the SBU does not match, managerial staff have no SKK, equipment does not meet the requirement, or the same person is proposed by two bidders. One checklist before uploading the bid prevents all of these.

QUALIFICATION CHECK, PACKAGE M8Same SBU subclass: yesSKK for all staff: yesStaff used by another bidder: noOwned or hired plant + proof: yesActive jobs < SKP limit: yesKSWP valid today: yes✓ 📷 3
A last check before uploading the bid.

Qualification checklist

CheckedRequirementNote
NIB and SBUSubclassification and qualification as in the LDPAn "equivalent" code or higher qualification is not automatically accepted
Managerial staffSKK matching the role in the LDPSmall packages usually ask for a project manager, technical manager, finance manager and safety officer
ExperienceUsually similar work in the last 4 yearsContracts and handover certificates as proof; check the LDP
Remaining package capacity (SKP)SKP = KP minus packages in progress; KP is 5 for small firms, 6 for othersThe Pokja checks against ongoing work data
Basic capability (KD)KD = 3 × NPt for medium and large firmsNPt = highest experience value in 15 years
Main equipmentOwned, hire purchase, or hired with an agreement and the lessor’s proof of ownershipA support letter alone is not accepted
TaxValid KSWPCheck on the upload day
Bid securityOnly for an owner’s estimate (HPS) above Rp10 billion, 1 to 3% of HPSBank guarantee or surety bond

The SKP and KD formulas come from Permen PUPR 14/2020, still the standard for construction tender documents. Always check them against your package’s LDK.

Example: package M8 with an Rp3 bn budget

CheckExample companyResult
SKP, small firmKP 5, three packages in progressSKP = 2: may bid
StaffFour people with SKK, not used in any other bidPass
EquipmentOwn concrete mixer; hired vibrator with agreement and the lessor’s proof of ownershipPass
Bid securityHPS Rp2.9 bnNot needed (below Rp10 bn)

What is new in 2026

Before uploading

  1. Copy every qualification requirement from the LDK into your own checklist.
  2. Match the SBU code character by character.
  3. Lock staff per package and never use the same person in another bid.
  4. Work out SKP from the contracts actually in progress.
  5. Collect equipment proof: invoices or hire agreements with ownership proof.
  6. Check the KSWP and SBU validity on the upload day.

Rules in force in November 2026: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (September 2026), which replaced LKPP Regulation 12/2021. The rules are still in transition (LKPP Circular 3/2026), so what binds each package is that package’s tender documents (LDP and LDK) and the schedule in SPSE.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What most often fails a bid at qualification?

In official evaluation reports: an SBU that does not match, managerial staff without SKK, main equipment not as required, and the same person proposed by two bidders.

How is remaining package capacity (SKP) worked out?

SKP = KP minus the number of packages in progress. KP is 5 for small firms and 6 for others under Permen PUPR 14/2020.

When is bid security required?

For construction work with an owner’s estimate (HPS) above Rp10 billion, at 1 to 3% of HPS.