Official tender evaluation reports show the same pattern: bids fail because the SBU does not match, managerial staff have no SKK, equipment does not meet the requirement, or the same person is proposed by two bidders. One checklist before uploading the bid prevents all of these.
Qualification checklist
| Checked | Requirement | Note |
|---|---|---|
| NIB and SBU | Subclassification and qualification as in the LDP | An "equivalent" code or higher qualification is not automatically accepted |
| Managerial staff | SKK matching the role in the LDP | Small packages usually ask for a project manager, technical manager, finance manager and safety officer |
| Experience | Usually similar work in the last 4 years | Contracts and handover certificates as proof; check the LDP |
| Remaining package capacity (SKP) | SKP = KP minus packages in progress; KP is 5 for small firms, 6 for others | The Pokja checks against ongoing work data |
| Basic capability (KD) | KD = 3 × NPt for medium and large firms | NPt = highest experience value in 15 years |
| Main equipment | Owned, hire purchase, or hired with an agreement and the lessor’s proof of ownership | A support letter alone is not accepted |
| Tax | Valid KSWP | Check on the upload day |
| Bid security | Only for an owner’s estimate (HPS) above Rp10 billion, 1 to 3% of HPS | Bank guarantee or surety bond |
The SKP and KD formulas come from Permen PUPR 14/2020, still the standard for construction tender documents. Always check them against your package’s LDK.
Example: package M8 with an Rp3 bn budget
| Check | Example company | Result |
|---|---|---|
| SKP, small firm | KP 5, three packages in progress | SKP = 2: may bid |
| Staff | Four people with SKK, not used in any other bid | Pass |
| Equipment | Own concrete mixer; hired vibrator with agreement and the lessor’s proof of ownership | Pass |
| Bid security | HPS Rp2.9 bn | Not needed (below Rp10 bn) |
What is new in 2026
- Borrowed-name bidding (pinjam bendera) is explicitly banned by LKPP Regulation 3/2026: lending or using another firm’s name and passing on all the work. Subcontracting part of the work is still allowed. Sanctions can be rejection, termination and blacklisting.
- According to a summary of LKPP Circular 3/2026, a branch office set up less than 30 calendar days before the announcement can be a sign of borrowed-name bidding.
- Qualification data already verified in the system may not need proving again, unless it was updated.
- Beneficial ownership data is evaluated for procurements announced from 1 November 2026.
- Supplier performance ratings as a qualification requirement are postponed until the system feature is ready.
Before uploading
- Copy every qualification requirement from the LDK into your own checklist.
- Match the SBU code character by character.
- Lock staff per package and never use the same person in another bid.
- Work out SKP from the contracts actually in progress.
- Collect equipment proof: invoices or hire agreements with ownership proof.
- Check the KSWP and SBU validity on the upload day.
Rules in force in November 2026: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (September 2026), which replaced LKPP Regulation 12/2021. The rules are still in transition (LKPP Circular 3/2026), so what binds each package is that package’s tender documents (LDP and LDK) and the schedule in SPSE.
Common mistakes
- An SBU subclassification different from the one requested.
- Managerial staff without SKK or not meeting the role requirements.
- Main equipment backed only by a support letter.
- The same person proposed by two bidders, so all their bids fail.
- More packages in progress than SKP allows.
The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
What most often fails a bid at qualification?
In official evaluation reports: an SBU that does not match, managerial staff without SKK, main equipment not as required, and the same person proposed by two bidders.
How is remaining package capacity (SKP) worked out?
SKP = KP minus the number of packages in progress. KP is 5 for small firms and 6 for others under Permen PUPR 14/2020.
When is bid security required?
For construction work with an owner’s estimate (HPS) above Rp10 billion, at 1 to 3% of HPS.
References
- AHP: LKPP Regulation 3/2026, beneficial ownership and anti-collusion: borrowed-name ban, beneficial ownership
- PUPR standard tender document (Indonesian): evaluation rules