How to Enter Indonesian Government Tenders in 2026: NIB, SBU, an INAPROC Account and Finding Packages in SPSE

Steps for small and medium contractors to bid for Indonesian government construction work: the licences to prepare (NIB, SBU, SKK, KSWP), INAPROC and SIKaP accounts, finding packages in SIRUP and LPSE, direct procurement and small business thresholds, and first-time mistakes.

Komander.ai Panduan team · 5 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Government tenders are open to every contractor whose licences match the package, and packages with a budget up to Rp15 billion are reserved for small businesses. What stops many contractors before they start is preparation: an SBU code that does not match, an invalid tax status, or an account that is not ready when the right package appears.

NPWP and NIBStaff SKKSBUValid KSWPINAPROC accountFind packages
Getting ready to bid for government work.

What to prepare

Document or accountWhat forNote
Company tax number (NPWP) and deedCompany identityData must match across every system
Business ID (NIB) through OSS with construction KBLI codesBusiness licenceKBLI must line up with the SBU subclassification
Business certificate (SBU)Required for every construction business (UU 2/2017 article 30)Subclassification and qualification must match the package
Staff competence certificates (SKK)Required for managerial and responsible staffStaff without SKK are not counted
Valid tax status confirmation (KSWP)Proof of tax complianceChecked in the tender documents
INAPROC accountAccess to the national procurement servicesFace and ID card check, one ID number per account

The construction licensing rule is now Permen PU 6/2025 (replacing Permen PUPR 6/2021). The order above is the most logical one, because the SBU needs the NIB and staff SKK; no single rule sets the order.

INAPROC and SIKaP accounts

Since an LKPP deputy’s letter of 17 November 2025, suppliers are asked to create an INAPROC account at akun.inaproc.id: personal email, a phone OTP code, a company profile with NIB, NPWP and VAT registration letter, then face verification and an ID card photo for the electronic certificate. One ID number is allowed one account. Until the old SPSE is shut down, the old SPSE and SIKaP logins still work. Verified supplier data can be used at every LPSE. Ask your nearest LPSE whether it still checks original documents.

The thresholds that set your chances

ValueRuleBasis
Up to Rp400 millionConstruction may be bought by direct procurement (pengadaan langsung)Perpres 46/2025 article 1
Budget up to Rp15 billionReserved for micro and small businesses and cooperatives, unless the work needs technical ability small firms lackPerpres 46/2025 article 65(3)
Owner’s estimate (HPS) above Rp10 billionBid security of 1 to 3% of HPS requiredPerpres 46/2025 article 30
Contract above Rp200 millionPerformance security of 5% of contract value (5% of HPS if the bid is below 80% of HPS)Perpres 46/2025 article 33

Since 1 September 2026, LKPP Regulation 2/2026 has also opened the electronic catalogue to construction work, with priority for local businesses, so some work is bought by e-purchasing rather than by tender.

Example: a first package in Bekasi, West Java

ItemAmountWhat it means
Budget for an office building refurbishmentRp1.8 bnUnder Rp15 bn: reserved for small businesses
Owner’s estimate (HPS)Rp1.75 bnUnder Rp10 bn: no bid security
Bid after correctionRp1.6 bn (91% of HPS)Above 80% of HPS: no price reasonableness check
Performance security if you winRp80 m (5% of Rp1.6 bn)Arrange a bank guarantee facility before bidding

Finding and following a package

  1. Watch this year’s procurement plans in SIRUP for agencies in your area.
  2. Check tender announcements on the agency’s LPSE (spse.inaproc.id/agency-name) and match the SBU subclassification, qualification and location.
  3. Download the tender documents and read the LDP and LDK before deciding to bid.
  4. Follow the clarification meeting (aanwijzing) in SPSE and download every addendum.
  5. Upload the bid before the deadline; do not wait for the last hour.
  6. Watch the evaluation result. To object, file a sanggah within 5 calendar days of the award announcement (ending on a working day and hour); the exact dates are in the SPSE schedule.

Rules in force in November 2026: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (September 2026), which replaced LKPP Regulation 12/2021. The rules are still in transition (LKPP Circular 3/2026), so what binds each package is that package’s tender documents (LDP and LDK) and the schedule in SPSE. Since 1 November 2026 bidders’ beneficial ownership data is also evaluated.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What do I need to bid for government construction work?

An NIB with construction KBLI codes, an SBU whose subclassification and qualification match the package, staff with SKK, a valid tax status (KSWP) and a procurement account (INAPROC, or SPSE/SIKaP during the transition).

Which packages are reserved for small contractors?

Packages with a budget up to Rp15 billion are reserved for micro and small businesses and cooperatives (Perpres 46/2025 article 65(3)), unless the work needs technical ability small firms lack.

What is the direct procurement limit for construction?

Up to Rp400 million under Perpres 46/2025.