How to Read Tender Documents, the RKS and the Aanwijzing: What to Check Before Pricing

What is in an Indonesian construction tender document (IKP, LDP, LDK, SSUK, SSKK, RKS, drawings, BoQ), how to read it in three layers, the rules for the clarification meeting (aanwijzing) and addenda in SPSE, the contract numbers to check, and common mistakes.

Komander.ai Panduan team · 4 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

A tender document can run to hundreds of pages, but only part of it changes your price and risk. Read it in three layers: the rules of the competition, what you price and build, and the contract you will sign. Then use the aanwijzing to close every open question, because after that only addenda bind.

Download docsRead the LDPCheck drawingsAsk questionsCheck addendaPrice the bid
The order for reading tender documents.

The tender document in three layers

LayerSectionsWhat to look for
Rules of the competitionInstructions to Bidders (IKP), Bid Data Sheet (LDP), Qualification Data Sheet (LDK)Evaluation method, qualification, schedule, securities. Package details are in the LDP and LDK
What you price and buildRKS or technical specification, drawings, bill of quantities (BoQ)Scope, quality, quantities, method
The contractGeneral Conditions (SSUK), Special Conditions (SSKK), draft contractPayment, advance, retention, penalties, securities, duration

Contract numbers to check

ItemUsual terms in the model documentsWhere
Contract typeLump sum: total fixed, quantity risk on the contractor. Unit price: unit rates fixed, total follows quantitiesLDP, SSKK
Advance paymentUp to 20% of contract value, 15% for multi-year contractsSSKK
Retention5% held during the maintenance period, or a 5% maintenance guarantee insteadSSUK, SSKK
Delay penalty1 per mil per day of the contract value or the unfinished part, as the SSKK saysSSKK
Performance security5% of contract value for contracts above Rp200 million (5% of HPS if the bid is below 80% of HPS)LDP
Construction safety plan (RKK)Must be attached to the bid (Permen PUPR 10/2021 article 13)LDP

Items left unpriced are deemed included in other prices and must still be built. Contracts also have a clause on the order of documents if they conflict; the order is not the same in every contract, so read that clause in your package’s draft contract.

Aanwijzing and addenda

Example: aanwijzing questions for a block M8 drain

Found while readingQuestion askedIf the answer changes the scope
Drawings show a 120 m drain, the BoQ says 100 mWhich quantity applies?Ask for it in an addendum
The concrete specification gives no gradeWhich concrete grade is required?Ask for it in an addendum
Narrow truck access to the siteMay we use temporary land on the east side?Record it in the BAPP, check on the site visit

Reading steps

  1. Read the LDP and LDK first to decide whether to bid.
  2. Check BoQ quantities against the drawings for the highest value items.
  3. Mark specifications that are unclear or conflicting.
  4. Send questions during the aanwijzing, short and with page references.
  5. Download the BAPP and every addendum, then update your estimate.
  6. Only then price the bid and write the method statement.

Rules in force in November 2026: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (September 2026), which replaced LKPP Regulation 12/2021. The rules are still in transition (LKPP Circular 3/2026), so what binds each package is that package’s tender documents (LDP and LDK) and the schedule in SPSE.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is the RKS?

Rencana Kerja dan Syarat-syarat: the technical conditions attachment describing scope, quality and methods. In government tenders it serves as the technical specification in the tender document.

Is attending the aanwijzing mandatory?

It is usually not grounds for rejection, but every addendum issued still binds bidders.

Are aanwijzing answers binding?

Only once put into an addendum. A change to the tender document that is not in an addendum is treated as not existing.

References

  1. Permen PUPR 14/2020 (Indonesian): clarification and addenda
  2. Permen PUPR 10/2021 (Indonesian): safety plan in the bid