A tender document can run to hundreds of pages, but only part of it changes your price and risk. Read it in three layers: the rules of the competition, what you price and build, and the contract you will sign. Then use the aanwijzing to close every open question, because after that only addenda bind.
The tender document in three layers
| Layer | Sections | What to look for |
|---|---|---|
| Rules of the competition | Instructions to Bidders (IKP), Bid Data Sheet (LDP), Qualification Data Sheet (LDK) | Evaluation method, qualification, schedule, securities. Package details are in the LDP and LDK |
| What you price and build | RKS or technical specification, drawings, bill of quantities (BoQ) | Scope, quality, quantities, method |
| The contract | General Conditions (SSUK), Special Conditions (SSKK), draft contract | Payment, advance, retention, penalties, securities, duration |
Contract numbers to check
| Item | Usual terms in the model documents | Where |
|---|---|---|
| Contract type | Lump sum: total fixed, quantity risk on the contractor. Unit price: unit rates fixed, total follows quantities | LDP, SSKK |
| Advance payment | Up to 20% of contract value, 15% for multi-year contracts | SSKK |
| Retention | 5% held during the maintenance period, or a 5% maintenance guarantee instead | SSUK, SSKK |
| Delay penalty | 1 per mil per day of the contract value or the unfinished part, as the SSKK says | SSKK |
| Performance security | 5% of contract value for contracts above Rp200 million (5% of HPS if the bid is below 80% of HPS) | LDP |
| Construction safety plan (RKK) | Must be attached to the bid (Permen PUPR 10/2021 article 13) | LDP |
Items left unpriced are deemed included in other prices and must still be built. Contracts also have a clause on the order of documents if they conflict; the order is not the same in every contract, so read that clause in your package’s draft contract.
Aanwijzing and addenda
- The clarification meeting is held in SPSE and recorded in the clarification minutes (BAPP).
- A site visit is optional and at your own cost; its results go into the BAPP.
- Any change to the tender document must be issued as an addendum. A change not in an addendum is treated as not existing, so an answer in the Q&A forum does not bind until it is put into an addendum.
- Addenda are issued at the latest about 3 days before the bid deadline; if more time is needed the deadline is extended. Permen PUPR 14/2020 and LKPP Regulation 3/2026 count those days differently, so follow the SPSE schedule.
- Missing the aanwijzing is usually not grounds for rejection, but bidders are still bound by every addendum.
Example: aanwijzing questions for a block M8 drain
| Found while reading | Question asked | If the answer changes the scope |
|---|---|---|
| Drawings show a 120 m drain, the BoQ says 100 m | Which quantity applies? | Ask for it in an addendum |
| The concrete specification gives no grade | Which concrete grade is required? | Ask for it in an addendum |
| Narrow truck access to the site | May we use temporary land on the east side? | Record it in the BAPP, check on the site visit |
Reading steps
- Read the LDP and LDK first to decide whether to bid.
- Check BoQ quantities against the drawings for the highest value items.
- Mark specifications that are unclear or conflicting.
- Send questions during the aanwijzing, short and with page references.
- Download the BAPP and every addendum, then update your estimate.
- Only then price the bid and write the method statement.
Rules in force in November 2026: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (September 2026), which replaced LKPP Regulation 12/2021. The rules are still in transition (LKPP Circular 3/2026), so what binds each package is that package’s tender documents (LDP and LDK) and the schedule in SPSE.
Common mistakes
- Pricing from the document version before the addendum.
- Treating aanwijzing answers as binding without an addendum.
- Not checking the BoQ against drawings on a lump sum contract, so missing quantities become your loss.
- Not reading the SSKK: penalties, advance and payment terms.
- Forgetting to attach the RKK.
The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
What is the RKS?
Rencana Kerja dan Syarat-syarat: the technical conditions attachment describing scope, quality and methods. In government tenders it serves as the technical specification in the tender document.
Is attending the aanwijzing mandatory?
It is usually not grounds for rejection, but every addendum issued still binds bidders.
Are aanwijzing answers binding?
Only once put into an addendum. A change to the tender document that is not in an addendum is treated as not existing.
References
- Permen PUPR 14/2020 (Indonesian): clarification and addenda
- Permen PUPR 10/2021 (Indonesian): safety plan in the bid