Allocating Head Office Overhead to Projects: Choosing the Base and Seeing True Project Profit

How to spread head office costs over construction projects: telling direct cost, project overhead and head office overhead apart, the allocation bases (direct cost, labour, revenue), an example that flips which project looks most profitable, the link to overhead and profit in AHSP, and the treatment under PSAK 115.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Office rent, directors’ pay, estimators and accounting are not part of any one project, but every project must cover them. Without allocation each project looks more profitable than it is, and the next bid can be too cheap. How you share them can even flip which project looks most profitable.

70%15%15%
  • Direct job cost
  • Project overhead
  • Head office overhead
A contractor’s three cost tiers (example) · only head office overhead needs allocating to projects.

Three cost tiers

TierExampleRecorded to
Direct costMaterials, labour, subcontractors, plant hireThe project directly
Project overheadSite supervisor, site office, temporary power, safetyThe project directly
Head office overheadOffice rent, directors and office staff, estimators, accountingShared over projects by an allocation base

Allocation rate = total head office overhead ÷ total allocation base. Common bases: direct cost, direct labour, labour hours, equipment hours or revenue. Revenue suits bid pricing poorly, because revenue is the very figure being set.

Example: the base flips the ranking

Head office overhead Rp300 m. Project A (equipment heavy): revenue Rp1.2 bn, direct cost Rp800 m, of which labour Rp100 m. Project B (labour heavy): revenue Rp1 bn, direct cost Rp600 m, of which labour Rp400 m.

Allocation baseProject A: share / marginProject B: share / margin
Labour (rate 60% of labour)Rp60 m / 28%Rp240 m / 16%
Direct cost (rate about 21.4%)about Rp171 m / 19%about Rp129 m / 27%
Revenueabout Rp164 m / 20%about Rp136 m / 26%

On a labour base project A looks most profitable; on direct cost or revenue, project B does. Because AHSP (Permen PUPR 8/2023) adds overhead and profit as a percentage on direct cost, a direct-cost base is a sensible starting point. Contractors who self-perform a lot of labour should also test a labour base.

For bids and the books

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is overhead allocation?

Sharing head office costs that belong to no single project over all projects using one base, such as direct cost or labour.

Which base is best?

Direct cost is a sensible starting point because it matches how AHSP adds overhead. Contractors who self-perform a lot of labour should also test a labour base.

Is head office overhead a contract cost in the accounts?

Usually not. Under PSAK 115, general and administrative costs are expensed as incurred unless the contract explicitly allows them to be charged to the client.