KomanderGuides
2 · ConstructionFinance / PRACTICAL GUIDE

How to Prepare a Monthly Certificate (MC) and Progress Certificate for Billing

How to prepare a construction monthly certificate (MC): MC-0, monthly MCs and MC-100, joint measurement, the progress certificate, and working out this month’s bill after down payment, retention and tax deductions.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

An MC (Monthly Certificate) records the value of work completed to the end of the month, based on a joint measurement by the contractor and the supervisor. The MC is the basis of the progress certificate, and the progress certificate is the basis of the progress bill. Without a tidy MC, bills get rejected or paid late.

to last month 35%this month 10%remaining 55%
Cumulative progress: 35% to last month plus 10% this month; this month’s bill comes from that 10% after deductions.

Kinds of MC

MCWhenContents
MC-0At the start, after a joint site measurementContract quantities adjusted to real conditions; can lead to an addendum
Monthly MC (MC-1, MC-2, ...)At the end of every monthQuantity installed per item to date, to last month, and this month alone
MC-100When the work is completeFinal quantities of all work; basis for handover and the last bill

What a monthly MC contains

ColumnExample for item II.2 Stone foundation
Code and descriptionII.2 Stone foundation
Contract quantity and unit price10.71 m3 × Rp1,120,000
Quantity to last month6.00 m3
Quantity this month3.50 m3
Quantity to date9.50 m3 (88.7%)
Value to date9.50 × Rp1,120,000 = Rp10,640,000
Contribution to project progressItem weight × percent complete

Working out this month’s bill

An example: a Rp1 billion contract (before VAT) with a 20% down payment and 5% retention. Progress was 35% to last month and is 45% to this month.

ItemAmount
Value of work to date (45%)Rp450,000,000
Minus value to last month (35%)minus Rp350,000,000
Value of work this monthRp100,000,000
Down payment repayment (20%)minus Rp20,000,000
Retention 5%minus Rp5,000,000
This month’s bill (before VAT and income tax)Rp75,000,000

VAT is billed separately, and the client withholds final income tax when paying. Work out the cash actually received with the progress payment calculator.

Steps every month

  1. Agree the monthly cut-off date with the supervisor.
  2. Measure jointly: the quantity installed for every item worked on this month, counting only work that passes inspection.
  3. Fill the MC: quantities to last month, this month and to date, with take-off sheets and photos.
  4. Sign the inspection and progress certificates with the supervisor and the client.
  5. Prepare the progress bill with the MC and certificates attached, and record it as a receivable.
  6. Update the actual S-curve and the WIP report from the same MC.
Swipe sideways to see every column →
The tab in the free finance template used for this work, with fictional example rows.
The tab in the free finance template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to create a construction finance report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is an MC in construction?

A Monthly Certificate: the monthly value of work completed, from a joint measurement, used as the basis of the progress bill.

What is MC-0?

A joint measurement at the start of the project to adjust contract quantities to site conditions; the result can lead to an addendum.

How is this month’s bill worked out?

Value of work to date minus value to last month, then minus the down payment instalment and retention.

Who signs the MC?

The contractor and the supervisor who measured together, then the client approves it.

References

  1. PU Kutai Barat: Module 04 on completing construction contracts (Indonesian): MC-0, MC-100 and contract changes