How to Score Percent Progress on Site for Every Kind of Work

Four ways to score construction progress on site: installed quantity, weighted stages, units completed, and milestones for lump-sum items. A lightweight block wall example with blockwork, plaster and skim coat.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

Guessed progress ("about 70%") makes the S-curve, the MC and the cost report untrustworthy. For each kind of work, pick one measurable way to score it, write the rule down, and use the same rule every week.

60%25%15%
  • Blockwork 60%
  • Plaster 25%
  • Skim coat 15%
Example weighted stages for walls · progress = sum of weight × percent done of each stage.

Four ways to score progress

MethodUsed forExample
Installed ÷ planned quantityExcavation, concrete, walls, tiles: work that can be measured420 m2 of 600 m2 = 70%
Weighted stagesWork with several steps in sequenceRoof: frame 50%, covering 40%, ridge and fascia 10%
Units completedWork counted per pieceFrames installed 8 of 12 = 66.7%
MilestonesLump-sum itemsMobilisation: 50% when equipment arrives, 100% when ready to work

Example: walls of the 6 × 8 m house

From the BOQ article: 94.11 m2 of wall and 188.22 m2 of plaster. This week the blockwork is all done, 120 m2 is plastered, and the skim coat has not started.

StageWeightDoneContribution
Blockwork60%94.11 of 94.11 m2 = 100%60.0%
Plaster25%120 of 188.22 m2 = 63.8%15.9%
Skim coat15%0%0.0%
Wall progress75.9%

Rules for consistency

Swipe sideways to see every column →
The tab in the free template used for this work, with fictional example rows.
The tab in the free template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

How do I work out percent progress?

Pick one method for each kind of work: installed quantity, weighted stages, units completed, or milestones, and use the same method every week.

Does delivered material count as progress?

No. Progress is only work installed and passed by inspection.

How does item progress become project progress?

Multiply each item’s progress by its budget weight and add them up.