Crew Attendance, Daily Wages and Advances: How to Record Them Without Leaks

How to record attendance of skilled workers and labourers every day, work out weekly wages with overtime, record and deduct advances, and match labour-contract advances against site measurements.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

Wages are the largest regular cost on many projects, and they leak most often through attendance filled in later and advances with no record. Simple daily records prevent both, and also give productivity data for the next tender.

42%45%8%
  • Skilled Rp5.40 m
  • Labourers Rp5.76 m
  • Foreman Rp1.08 m
  • Overtime Rp0.60 m
One week’s wages: Rp12.84 m before advance deductions · Rp11.34 m paid after Rp1.5 m of advances.

Daily attendance

ColumnExample
Date23/06/2026
NameBudi
RoleSkilled worker
Present1 (full day), 0.5 (half day), 0
Overtime (hours)2
Work item codeIV.1 walls C5-08
Foreman’s initialssignature or tick on the form

Example: one week’s wages (6 working days)

ItemCalculationAmount
Skilled workers6 people × 6 days × Rp150,000Rp5,400,000
Labourers8 people × 6 days × Rp120,000Rp5,760,000
Foreman1 person × 6 days × Rp180,000Rp1,080,000
OvertimeBy recorded hoursRp600,000
Total wagesRp12,840,000
Advances deducted this weekminus Rp1,500,000
PaidRp11,340,000

Recording advances

Swipe sideways to see every column →
The tab in the free template used for this work, with fictional example rows.
The tab in the free template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

How are weekly wages for daily workers worked out?

Days present × each person’s daily rate, plus overtime, minus advance deductions.

How should crew advances be recorded?

Record the date, name, amount and signatures when given, then the deduction and balance each week.

What about advances to labour-contract crews?

Compare them with the value of work from the site measurement. If the advances are larger, the crew has been paid ahead.