Hired plant is paid by the hour or day, whether it works or waits. Cost usually leaks not through the rate but through paid hours with no output: waiting for trucks, waiting for an operator, breakdowns, or no work ready. A daily record of plant hours shows where the leak is.
- Working 34 h
- Waiting for trucks 10 h
- Breakdown 4 h
- No work 8 h
Daily plant timesheet
| Column | Example |
|---|---|
| Plant and unit number | 0.8 m3 excavator, unit EX-02 |
| Hour meter start and end | 1,204 and 1,212 = 8 hours |
| Working hours | 5 hours drain excavation at block M8 |
| Waiting hours and why | 2 hours waiting for dump trucks |
| Breakdown hours | 1 hour hydraulic hose |
| Fuel added | 60 litres |
| Output | 160 m3 excavated |
| Initials | Operator and site supervisor |
The numbers to watch
- Utilisation = working hours ÷ paid hours. The example above is 34 ÷ 56 = 61%.
- Productivity = output ÷ working hours, compared with the figure in the unit price analysis.
- Fuel per working hour, to spot unusual use.
- Actual plant cost per m3 compared with the RAP.
What the hire contract must make clear
- Rate per hour or day, and the minimum hours per day or month.
- Who pays for the operator, fuel, maintenance, mobilisation and demobilisation.
- Breakdown hours are not paid, and the deadline to replace a unit.
- How hours are counted: hour meter readings initialled by both sides.
Hire rates vary by region, machine size and hire period, and quoted rates often exclude mobilisation, operator or fuel. Get quotes from several local providers and compare them on the same scope.
Common mistakes
- Paying the provider’s invoice without an initialled timesheet.
- Plant brought in before the work and trucks are ready.
- Breakdown hours paid.
- Actual productivity never compared with the unit price analysis.
The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
How is plant utilisation worked out?
Working hours divided by paid hours. Low utilisation means many waiting or breakdown hours.
What goes on a plant timesheet?
Hour meter start and end, working hours, waiting hours and why, breakdown hours, fuel, output, and the operator’s and supervisor’s initials.
What must the hire contract make clear?
Rates and minimum hours, who pays for operator, fuel, maintenance and mobilisation, and the rule for breakdown hours.