How to Measure Work Done (Opname) and Pay Labour Contractors

How to measure completed construction work (opname): measure installed quantities, work out percentage progress, and pay labour contractors from the result.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

An opname is a site measurement of completed work. It is used for two things: the project’s physical progress, and paying labour contractors. That is why it must be measured, not guessed.

How to measure

  1. Take the work items and planned quantities from the budget, for example 600 m2 of block wall.
  2. Measure the quantity installed on site, for example 420 m2.
  3. Work out the progress: 420 ÷ 600 = 70%.
  4. Record the date, who measured and who verified.
  5. Add a new row for every measurement; never overwrite the previous one.
  6. Count only work that passes inspection. Work that must be redone and material not yet installed do not count.
  7. For walls measured in m2, subtract door and window openings.
  8. Record the result in a measurement certificate (berita acara opname) signed by the foreman, site manager and supervisor, with photos.

Example: paying a labour contractor

ItemAmount
Labour contract, block wall600 m2 × Rp35,000 = Rp21,000,000
Progress from the measurement70%
Earned to date70% × Rp21,000,000 = Rp14,700,000
Already paid (earlier advances)Rp12,000,000
Can be paid nowRp2,700,000

When advances already paid are more than what has been earned, the crew has been paid ahead of the work. That can be fine, but it must be visible, because what is left of the contract is then smaller than the work left.

Swipe sideways to see every column →
The Upah Rencana vs Aktual tab
The Upah Rencana vs Aktual tab: planned quantity and labour cost beside the measured quantity, the measurement date and the cost status.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is an opname?

A site measurement of completed work, as a quantity or a percentage, used as the basis for progress and payment.

How is the percentage worked out?

Installed quantity divided by planned quantity. 420 m2 of 600 m2 is 70%.

When are labour contractors paid?

Usually after a measurement: the progress percentage times the contract value, minus what was already paid as advances.

Who verifies the measurement?

The site supervisor or consultant, so the reported progress and the payments can be justified.

References