Releasing Guarantees and Bank Guarantees After PHO and FHO: Order, Documents, and the Mistakes That Hold Money Back

When the advance payment guarantee, performance guarantee, retention and maintenance guarantee are released on Indonesian government construction projects, the documents needed, closing a bank guarantee at the bank, and the mistakes that hold guarantees or retention back.

Komander.ai Panduan team · 4 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Guarantees and retention tie up a contractor’s money: cash margin at the bank, guarantee facilities, and 5% of the contract value held back. That money is only freed when the paperwork is complete and in the right order. On government projects each guarantee has its own release point around first handover (PHO) and final handover (FHO).

123456789101112Advance guaranteePerformance guaranteeRetention / maintenanceMonth
Example guarantee periods: 8-month project, PHO in month 8, FHO in month 12.

When each guarantee is released

GuaranteeAmountValid untilNote
Advance payment guaranteeThe advance amountUntil the advance is fully deducted from progress payments, as the contract saysIts value falls with the advance still outstanding
Performance guarantee5% of contract value; 5% of the owner’s estimate (HPS) if the bid was below 80% of HPSFirst handover (PHO)Returned after PHO
Retention5% of contract valueHeld from PHO to FHOA payment mechanism, not a guarantee
Maintenance guarantee5% of contract valueEnd of the maintenance period (FHO)Instead of retention: the contractor gets 100% at PHO; returned within 14 working days after the maintenance period ends

At PHO the contractor chooses: receive 95% and leave 5% held as retention until FHO, or lodge a 5% maintenance guarantee and receive 100%. They are not the same: retention is money held back, a maintenance guarantee is a guarantee letter from a bank or guarantor.

Example: Rp1 bn contract, housing block M8

ItemAmountWhen released
5% performance guaranteeRp50 mAfter PHO
If the bid was below 80% of an Rp1.2 bn HPSRp60 m (5% of HPS)After PHO
Option A: 5% retentionRp50 m heldPaid after FHO
Option B: 5% maintenance guaranteeRp50 m, contractor receives 100% at PHOReturned after the maintenance period

Steps to get them back

  1. Keep the handover certificates (PHO, then FHO) and proof that the advance has been fully deducted.
  2. Send a written request for the guarantee to be returned to the contracting officer (PPK), attaching the certificates.
  3. Get the original guarantee or a release letter from the PPK. Electronic guarantees with a valid e-signature do not need a paper original.
  4. Take it to the bank or guarantor to close the facility and release the cash margin. If the original cannot be returned, banks usually ask for a stamped written statement.
  5. For retention, invoice it after FHO; do not wait to be asked.

A bank guarantee ends when the original is returned, when the claim period passes with no claim, or when the beneficiary releases it in writing. Bank claim periods are usually 14 to 30 days after expiry. All government project guarantees are unconditional and are paid by the issuer within 14 working days of the order to pay.

Legal basis for government projects: Perpres 16/2018 as last amended by Perpres 46/2025, and LKPP Regulation 3/2026 (set in September 2026, replacing LKPP Regulation 12/2021). Tenders started before the new rule and contracts already signed still follow the old rule and their contract terms. Private projects have no specific rule: retention and guarantees follow the contract. A FIDIC 2017 contract, for example, releases half the retention at taking over and half after the defects period.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

When is the performance guarantee returned?

After first handover (PHO) of the construction work, because it is valid until PHO.

What is the difference between retention and a maintenance guarantee?

Retention is 5% of payment held until FHO. A maintenance guarantee is a 5% guarantee letter lodged so the contractor receives full payment at PHO.

How soon is the maintenance guarantee returned?

Within 14 working days after the maintenance period ends, on government projects.

References

  1. LKPP legal database: consolidated Perpres 16/2018 to 46/2025 (Indonesian): advance and maintenance guarantees
  2. Fenwick Elliott: contractual liabilities after completion: FIDIC retention release