After handover, buyers will find defects: a leaking roof, hollow tiles, hairline cracks, a sticking door. How the developer handles them decides the project’s reputation and the next phase’s sales. The key is to log every complaint per unit, fix it within the promised time, and pass the cost on to the responsible contractor or subcontractor.
The maintenance period and its basis
- The house sale agreement (PPJB) includes building maintenance terms (Permen PUPR 11/PRT/M/2019 on the PPJB system). The period and claim process must be written clearly in the PPJB.
- In practice, developers’ warranty claim periods are often about 3 months or 100 days after handover; some give longer for structure or roof. Check your PPJB.
- The developer’s contract with the contractor should have a maintenance period and retention no shorter than the promise to buyers.
Complaint log per unit
| No | Unit | Date | Complaint | Cause | Responsible | Due | Status |
|---|---|---|---|---|---|---|---|
| K-031 | M8-07 | 3 Nov | Roof leak in the front bedroom | Tile joint | Roofing subcontractor | 10 Nov | Scheduled |
| K-032 | M8-09 | 4 Nov | 4 hollow floor tiles | Too little mortar | Flooring foreman | 14 Nov | Open |
| K-033 | M8-07 | 4 Nov | Bathroom door sticks | Frame swelling | Contractor | 8 Nov | Done |
Stopping repeat complaints
- Group complaints by work type every month; frequent types get the method fixed on the next units.
- Check a defects list before handover, so buyers receive an inspected house.
- Repair costs come out of the responsible subcontractor’s or foreman’s retention, as the contract says.
- Put a complaint summary into the final project report and the subcontractor ratings.
Common mistakes
- Complaints taken by phone and never logged.
- No repair deadline promised to the buyer.
- Subcontractor retention paid before the maintenance period to buyers ends.
- Complaint data not used to improve the next units.
The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
How long is a developer’s house warranty?
As the PPJB says. Permen PUPR 11/PRT/M/2019 requires the PPJB to include maintenance terms; in practice often about 3 months, sometimes longer for structure or roof.
Who pays for repairs after handover?
The developer is responsible to the buyer; the cost is passed on to the contractor or subcontractor under their contract and maintenance period.
What goes in the complaint log?
Unit, date, the complaint with photos, cause, who is responsible, deadline and status.