Project Handover (PHO and FHO): Checklist, Maintenance Period and Closing the Project Books

How to close a construction project: the checklist before first handover (PHO), the defects list, the maintenance period, 5% retention or a maintenance guarantee, final handover (FHO), and closing the project accounts.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

The end of a project is often the messiest part: the work is done, but defects are still open, retention is forgotten, and the project’s profit is never worked out again. Handover happens twice: the first handover (PHO, Provisional Hand Over) when the work is 100% complete, and the final handover (FHO, Final Hand Over) after the maintenance period.

Maintenance period, at least 6 monthsWork 100%PHOFHORetention paid95%5%
From 100% complete to final handover: 95% paid at PHO, the 5% retention released after FHO.

Checklist before PHO

Maintenance period and retention

During the maintenance period the contractor must fix any defects that appear. On Indonesian government projects, the PUPR handover procedure sets a maintenance period of at least 6 months for permanent work and 3 months for semi-permanent work. After PHO, 95% of the contract price is paid; 5% is held as retention, or paid in full if the contractor provides a maintenance guarantee. Private projects follow their contract.

ItemExample: Rp1 billion contract
Paid by PHO95% = Rp950 m (before tax deductions)
Retention held5% = Rp50 m
Maintenance period6 months after PHO
Retention releasedAfter the FHO is approved

Final handover (FHO)

  1. Near the end of the maintenance period, ask for a joint inspection.
  2. Fix every defect found and record it in minutes.
  3. Sign the final handover certificate.
  4. Bill the retention, or ask for the maintenance guarantee to be returned.

Closing the project books

A note for property developers

Handing a unit to a buyer uses a unit handover certificate, with a complaints list fixed during the warranty period. Record each complaint with the date reported and the date fixed; it is also the basis for rating the contractor who built the unit.

Swipe sideways to see every column →
The tab in the free cost template used for this work, with fictional example rows.
The tab in the free cost template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is the difference between PHO and FHO?

PHO (first handover) is when the work is 100% complete. FHO (final handover) is after the maintenance period ends and defects are fixed.

How long is the maintenance period?

As the contract says. On Indonesian government projects, the PUPR procedure sets at least 6 months for permanent work and 3 months for semi-permanent work.

When is retention paid?

After the FHO is approved, or in full at PHO if the contractor provides a maintenance guarantee.

What is a punch list?

A list of defects or unfinished work made with the client before handover, then fixed one by one.