How to Track Project Retention and When It Is Released

How to fill the Retensi tab: contract value, retention percentage, retention held, expected release date and release conditions.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

Retention is the part of each payment the client holds back until the maintenance period ends, usually 5% of the contract value. The money is yours but cannot be used yet.

Tracking retention separately makes sure it is not counted as available cash, and is not forgotten when the maintenance period ends.

Where the numbers come from

Columns and how to fill them

Tab Retensi in the free finance template. The examples are fictional. Withheld retention is not available cash. Rates and release dates follow the contract.

ColumnExampleHow to fill it
Proyek/BlokE2The project or block this row belongs to, for example C4. One row is for one project only.
Pemberi Kerja / BankPemberi Kerja ContohWho holds the retention: the client, or the bank for mortgages (KPR).
No. Kontrak/BADEMO-KON-001The contract or handover document number the retention comes from.
Nilai Kontrak (IDR)1000000000The contract value the retention is taken from, in rupiah.
Retensi (%)5The percentage held back from the contract, for example 5 for 5%.
Retensi Ditahan (IDR)50000000Example: Rp1,000,000,000 × 5% = Rp50,000,000. Reconcile actual retention withheld.
Perkiraan Tanggal Cair31/03/2027Use a date supported by contract conditions; do not treat it as already received.
Syarat PencairanBA pemeliharaan disetujuiRecord documents or conditions required before release.
KeteranganContoh; belum diterimaExtra notes that help explain the row, for example a confirmation status or the reason for a change. May be blank.
Swipe sideways to see every column →
The Retensi tab in the free finance template, with fictional example rows.
The Retensi tab in the free finance template, with fictional example rows.

How to check it

  1. Retention held matches the retention deducted from every payment received.
  2. The expected release date is the end of the maintenance period in the contract.
  3. The release condition is written clearly, for example maintenance certificate approved.

Common mistakes

Start from a template

The full guide is in How to create a construction finance report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What percentage is retention usually?

Commonly 5% of the contract value, but follow your contract.

When is retention released?

After the maintenance period ends and the final handover (FHO) is approved.

Can retention be replaced by a guarantee?

Often yes: a bank or insurance maintenance guarantee replaces it, so payments are made in full.