Shop Drawings, RFIs and Submittals: The Approval Flow That Keeps Work Moving

The difference between shop drawings, RFIs and material submittals on a construction project, the submission and approval flow, an example tracking log, and how to stop work being held up or redone for lack of approval.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

Before much of the work can start, the contractor needs approvals: detailed shop drawings, material samples or data sheets (submittals), and answers to unclear drawings (RFIs). If submissions are late or not tracked, work is held up; if work starts before approval, the contractor carries the risk, including tearing it out.

Contractor preparesSubmit to supervisorReviewApproved / reviseThen buildLog it
The shop drawing and submittal flow.

The difference

DocumentWhat it is forExample
Shop drawingDetailed construction drawings by the contractor or subcontractor, based on the design drawingsLight steel roof frame details, stair reinforcement details
Material submittalSamples, data sheets or certificates approved before purchaseTile sample, pump data sheet, rebar test certificate
RFI (Request for Information)A written question when drawings or specifications are unclear, conflicting or do not match the siteDrain levels differ between the architectural and civil drawings

Tracking log

NoTitleSubmittedReply dueStatusWork waiting on it
SD-012Roof frame block M820 Oct27 OctApproved with commentsRoof installation week 18
MS-021Floor tiles 40×4028 Oct4 NovWaitingTile purchase
RFI-007Drain levels block M830 Oct6 NovOpenDrain excavation

Steps

  1. List every shop drawing and submittal needed from the specification and schedule, with the latest date to submit.
  2. Submit early enough for the review time in the contract (for example 7 days).
  3. For RFIs, write a clear question with drawings and a proposed answer.
  4. Do not start work or fabrication before approval.
  5. Raise late items at the weekly meeting and record delays they cause, as evidence for a time claim.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is a shop drawing?

A detailed construction drawing prepared by the contractor or subcontractor from the design drawings, approved before the work is done.

What is an RFI?

A written request for information from the contractor when drawings or specifications are unclear, conflicting or do not match the site.

May work start before the shop drawing is approved?

Better not. Work before approval is the contractor’s risk, including tearing it out.

References

  1. Fieldwire: RFIs, submittals and specifications: definitions
  2. Procore: the construction submittal process: submission and approval flow