Before much of the work can start, the contractor needs approvals: detailed shop drawings, material samples or data sheets (submittals), and answers to unclear drawings (RFIs). If submissions are late or not tracked, work is held up; if work starts before approval, the contractor carries the risk, including tearing it out.
The difference
| Document | What it is for | Example |
|---|---|---|
| Shop drawing | Detailed construction drawings by the contractor or subcontractor, based on the design drawings | Light steel roof frame details, stair reinforcement details |
| Material submittal | Samples, data sheets or certificates approved before purchase | Tile sample, pump data sheet, rebar test certificate |
| RFI (Request for Information) | A written question when drawings or specifications are unclear, conflicting or do not match the site | Drain levels differ between the architectural and civil drawings |
Tracking log
| No | Title | Submitted | Reply due | Status | Work waiting on it |
|---|---|---|---|---|---|
| SD-012 | Roof frame block M8 | 20 Oct | 27 Oct | Approved with comments | Roof installation week 18 |
| MS-021 | Floor tiles 40×40 | 28 Oct | 4 Nov | Waiting | Tile purchase |
| RFI-007 | Drain levels block M8 | 30 Oct | 6 Nov | Open | Drain excavation |
Steps
- List every shop drawing and submittal needed from the specification and schedule, with the latest date to submit.
- Submit early enough for the review time in the contract (for example 7 days).
- For RFIs, write a clear question with drawings and a proposed answer.
- Do not start work or fabrication before approval.
- Raise late items at the weekly meeting and record delays they cause, as evidence for a time claim.
Common mistakes
- Submitting close to the work date, so work is held up.
- Building before approval, then having to tear it out.
- RFIs raised verbally, leaving no evidence when there is a delay.
- No tracking log, so unanswered submissions are forgotten.
The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
What is a shop drawing?
A detailed construction drawing prepared by the contractor or subcontractor from the design drawings, approved before the work is done.
What is an RFI?
A written request for information from the contractor when drawings or specifications are unclear, conflicting or do not match the site.
May work start before the shop drawing is approved?
Better not. Work before approval is the contractor’s risk, including tearing it out.
References
- Fieldwire: RFIs, submittals and specifications: definitions
- Procore: the construction submittal process: submission and approval flow