The weekly coordination meeting brings the contractor, supervisor and client together to cover progress, problems and the decisions needed. A good meeting is short, uses the weekly report as its material, and ends with an action list: who does what, by when. Without it, the same problems come back next week.
Fixed agenda
| Order | Topic | Material |
|---|---|---|
| 1 | Last week’s actions: done or not | Action list |
| 2 | Planned against actual progress, deviation | S-curve and weekly report |
| 3 | Site problems and decisions needed | Daily reports, open RFIs |
| 4 | Materials, plant and labour for the next two weeks | Procurement schedule |
| 5 | Quality and safety | Open NCRs, safety report |
| 6 | Changes and billing | Variation list, payment certificate |
Example action list in the minutes
| No | Action | Owner | Due | Status |
|---|---|---|---|---|
| 14.1 | Answer RFI-007 on drain levels at block M8 | Design consultant | 6 Nov | Open |
| 14.2 | Add 1 wall gang to recover the minus 2.4% deviation | Contractor | 4 Nov | Open |
| 14.3 | Approve the floor tile sample | Client | 5 Nov | Open |
| 13.2 | Close NCR-014 on concrete cover | Rebar foreman | 30 Oct | Done |
Making it useful
- Send the weekly report a day before the meeting.
- Keep it to 60 minutes; detailed technical issues go to a separate session.
- Send the minutes within a day and approve them at the next meeting.
- Decisions that change cost or time go into a letter or change order, not just the minutes.
Common mistakes
- A meeting with no agenda or material, so it is only story telling.
- Minutes with no owner or due date.
- Last week’s actions not checked.
- Changes agreed in the meeting but never put in a written instruction.
The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.
Ready to use the Komander agents on your projects?
When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.
Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.
Common questions
What goes in project meeting minutes?
Date and attendees, a progress summary, decisions, and an action list with owners and due dates.
Who attends the weekly coordination meeting?
The contractor’s project manager, the supervisor or project manager (MK), the client’s representative, and where needed the designer and main subcontractors.
Are minutes enough for a change in the work?
No. Changes in cost or time must go into a written change order or amendment.