Weekly Project Coordination Meeting: Agenda, Minutes and Action List

How to run a short, useful weekly construction coordination meeting: who attends, a fixed agenda built on the weekly report, example minutes, and an action list checked every week.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

Edited by Ravi MelwaniCEO & Co-founder, Komander.ai

Prices and rules are summarised from the sources listed below and updated regularly. Check local prices and the relevant authority before relying on them.

The weekly coordination meeting brings the contractor, supervisor and client together to cover progress, problems and the decisions needed. A good meeting is short, uses the weekly report as its material, and ends with an action list: who does what, by when. Without it, the same problems come back next week.

Weekly reportFixed agenda60-minute meetingMinutesFollow-upCheck next week
The weekly coordination meeting cycle.

Fixed agenda

OrderTopicMaterial
1Last week’s actions: done or notAction list
2Planned against actual progress, deviationS-curve and weekly report
3Site problems and decisions neededDaily reports, open RFIs
4Materials, plant and labour for the next two weeksProcurement schedule
5Quality and safetyOpen NCRs, safety report
6Changes and billingVariation list, payment certificate

Example action list in the minutes

NoActionOwnerDueStatus
14.1Answer RFI-007 on drain levels at block M8Design consultant6 NovOpen
14.2Add 1 wall gang to recover the minus 2.4% deviationContractor4 NovOpen
14.3Approve the floor tile sampleClient5 NovOpen
13.2Close NCR-014 on concrete coverRebar foreman30 OctDone

Making it useful

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What goes in project meeting minutes?

Date and attendees, a progress summary, decisions, and an action list with owners and due dates.

Who attends the weekly coordination meeting?

The contractor’s project manager, the supervisor or project manager (MK), the client’s representative, and where needed the designer and main subcontractors.

Are minutes enough for a change in the work?

No. Changes in cost or time must go into a written change order or amendment.