PBG and SLF: Indonesian Building Permits, Documents and Sequence

A guide to PBG (building approval) and SLF (certificate of fitness for use) for contractors and developers: the PP 16/2021 basis, the documents to prepare, the SIMBG sequence, and fitting them into the project schedule.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

Since PP 16/2021, the old IMB has been replaced by PBG (building approval), and a finished building needs an SLF (certificate of fitness for use) before it is used. PBG comes before building, SLF after. For contractors, both decide when work may start and when the building may be handed over, so they belong in the schedule from the start.

SIMBG accountUpload documentsExpert reviewLevyPBG issuedBuildSLF
From building permit to occupancy certificate.

Documents to prepare

GroupContentsPrepared by
ApplicantID card and tax number, or company deed and tax numberOwner or developer
Land and zoningLand certificate or land use agreement, zoning approval (KKPR)Owner or developer
Technical designArchitectural, structural and MEP drawings with calculationsDesign consultant
EnvironmentalDepending on scale, for example SPPL or UKL UPLOwner with a consultant
For SLFThe PBG, as-built drawings, a technical assessmentContractor and technical assessor

The sequence

  1. Create an account on SIMBG (simbg.pu.go.id) and enter the building details.
  2. Upload the documents. The technical design is reviewed by an expert panel (TPA) or technical assessment team; revise the drawings if asked.
  3. Once the design is approved, pay the regional levy.
  4. The PBG is issued. Construction may start, and the local government may inspect at certain stages.
  5. When finished, prepare the as-built drawings and the technical assessment, then apply for the SLF.
  6. The SLF is issued; the building may be used and handed over.

Putting it in the schedule

ActivityExample planned durationNote
Prepare and upload the PBG documents2 weeksAlongside the working drawings
Review and revisions2 to 6 weeksMost often late; ask the local office for an estimate
PBG issuedMilestoneStart physical work after this date
Technical assessment and SLF2 to 4 weeksStart at about 90% complete, do not wait for the end

The durations above are only planning examples. Review times differ by region, and the implementing rules keep changing (for example PP 28/2025 on risk-based licensing). Confirm the document list and levy with the local public works office or licensing office (DPMPTSP).

For housing estates: PBG per type, prototypes and the low-income route

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is the difference between PBG and SLF?

PBG is the approval before building, based on the technical design. SLF is the certificate after completion, stating the building is fit for use.

Is PBG the same as IMB?

PBG replaced IMB under PP 16/2021. IMBs issued before remain valid.

Where do I apply?

Through SIMBG (simbg.pu.go.id); the regional technical office and licensing office then process it.