Housing PBG per House Type: SIMBG Prototypes and the 10-Day Route for Low-Income Houses

How developers speed up building approval (PBG) for housing estates: a collective PBG per house type, 8 simple-house prototypes in SIMBG (Kepmen PUPR 2947/2024), and the three-minister decree that waives the PBG levy and BPHTB and cuts PBG for low-income (MBR) houses to 10 working days.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

For housing estates, the PBG is not applied for per unit but per house type. Since late 2024 there are two more shortcuts for simple and low-income (MBR) houses: prototype designs already in SIMBG, and a three-minister decree that removes the PBG levy and BPHTB and cuts the issuing time. Both save money and time, but each has conditions.

123456Normal PBG 28 daysMBR PBG 10 daysWorking week
PBG issuing deadline in working weeks (5 working days per week); the MBR route applies once the region has issued its Perkada.

Three shortcuts and their conditions

ShortcutWhat it isConditions and notes
Collective PBG per typeOne PBG for each house type in the estate, not per unitEach type still needs its own technical package; fewer types means faster review
SIMBG prototypes8 simple-house designs (Kepmen PUPR 2947/KPTS/M/2024, effective 18 October 2024), offered as options in SIMBGThe specification is standard so it is not re-checked; some regions also have their own prototypes
Three-minister decree (25 November 2024)PBG levy and BPHTB removed for MBR houses; PBG issued within 10 working days instead of 28Applies only once the region issues its implementing regulation (Perkada); buyers must meet the MBR criteria (Kepmen PUPR 22/Kpts/M/2023, for example landed houses up to 36 m2)

How much it saves

Each region works out the PBG levy as: floor area × locality index × unit price (SHST) × integrated index × built-building index. Because the values are set in each regional regulation, the amount differs by regency and city. Reporting when the decree was issued said removing BPHTB and the PBG levy could save up to about Rp10 m per house.

Example: 40 units, 2 typesWithout shortcutsWith prototypes and the MBR route
Number of PBGs2 (one per type)2 (one per type)
DesignDrawn and reviewed per typeChoose a prototype in SIMBG
Issuing deadline28 working days10 working days (with a Perkada)
PBG levyAs the regional regulation saysRp0 for MBR houses

Steps

  1. Ask the local licensing office (DPMPTSP) or public works office whether the Perkada implementing the decree has been issued.
  2. Make sure the house types and buyers meet the MBR criteria.
  3. Cut the number of house types; where suitable, use a prototype from SIMBG.
  4. Apply for a collective PBG per type in SIMBG after the zoning approval (KKPR) and environmental approval are done.
  5. Record the application and issue dates, so delays can be raised with the office.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

Is the PBG free for MBR houses?

Yes, the PBG levy and BPHTB are removed under the three-minister decree of 25 November 2024, but only in regions that have issued the implementing Perkada.

How long does an MBR PBG take?

At most 10 working days under the decree, against 28 working days for a normal PBG.

What is a SIMBG prototype?

A standard simple-house design from Kepmen PUPR 2947/KPTS/M/2024 that can be chosen directly in SIMBG, so the design is not reviewed again.

References

  1. CNBC Indonesia: three ministers remove BPHTB and PBG for MBR houses (Indonesian): decree of 25 November 2024
  2. Detik Properti: subsidised house prototype rule issued (Indonesian): Kepmen PUPR 2947/2024