Groundwater Permits (SIPA) for Project and Housing Bore Wells: Requirements, 14 Days, and No Drilling Before the Permit

When projects and housing estates need a groundwater permit: SIPA for business use through OSS and a use approval above 100 m3 a month, under Permen ESDM 14/2024; requirements, the 14-working-day deadline, meters, groundwater tax, and Jakarta’s special rules.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

Many projects drill a well early for construction water, and housing estates often use a shared bore well. Since Permen ESDM 14/2024, a new well may only be drilled after its permit is issued. The good news is that the process is simpler now: fewer requirements, no permit fee, and issue within 14 working days if the file is complete.

Technical studyApplyIssued in 14 daysDrill and pump testFit a meterReport and tax
Groundwater permit order: permit first, then drill.

Who needs which permit

UserPermitApplied through
Business (hotels, factories, commercial buildings, estates that sell water)Groundwater business permit (SIPA)OSS
Non-business above 100 m3 a month (households or groups)Groundwater use approval (PPAT)perizinan.esdm.go.id
Households below 100 m3 a monthNo approval needed

A shared well for an estate that does not sell water probably falls under PPAT if group use is above 100 m3 a month; confirm with the Geological Agency or the provincial energy office. Official sources word the threshold both as "at least" and "more than" 100 m3, so use the latest figure from the office.

Requirements and process

Putting it in the schedule

ActivityExample durationNote
Technical study1 to 2 weeksLonger for large businesses
Permit processingUp to 14 working daysIf the file is complete
Drilling and pumping test1 to 2 weeksThe pumping test is often 24 to 48 hours
While waitingWater from the utility or tankersPut the cost in the RAP

Groundwater tax and Jakarta rules

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

Does drilling a project well need a permit?

Yes for business use or above 100 m3 a month. Under Permen ESDM 14/2024, a new well may only be drilled after the SIPA or PPAT is issued.

How long does it take and what does it cost?

Up to 14 working days if the file is complete, with no permit fee. Groundwater tax is still paid by volume.

What is the difference between SIPA and PPAT?

SIPA is for groundwater used in a business, applied for through OSS. PPAT is for non-business use above 100 m3 a month, applied for through perizinan.esdm.go.id.

References

  1. Geological Agency (ESDM): groundwater permit FAQ (Indonesian): SIPA via OSS, PPAT, no drilling before the permit
  2. Ministry of Energy: easier groundwater permits (Indonesian): 3 requirements, 14 working days, free