How to Calculate Work Item Weights (Bobot) in Construction Projects, with an Example

How to work out the weight (%) of each work item from the budget, use weights for cumulative progress and the S-curve, a worked example, and the Excel formulas.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

A work item’s weight (bobot) is its share of the whole project’s value, as a percentage. Weights combine the progress of very different work into one project progress figure: finishing the roof does not mean the same as finishing site preparation, because they are worth different amounts.

The weight formula

Weight = value of the work item ÷ total value of all work × 100%. Values come from the budget (RAB): quantity × unit price. The weights of all work items always add up to 100%.

12%25%15%13%10%15%8%
  • Preparation 2%
  • Foundations 12%
  • Concrete structure 25%
  • Walls 15%
  • Roof 13%
  • Floors 10%
  • Finishing 15%
  • Electrical and plumbing 8%
Each work item’s weight, 100% in total

Example: a house with a Rp500 million budget

Work itemBudget valueWeight
PreparationRp10 m2%
FoundationsRp60 m12%
Concrete structureRp125 m25%
WallsRp75 m15%
RoofRp65 m13%
FloorsRp50 m10%
FinishingRp75 m15%
Electrical and plumbingRp40 m8%
TotalRp500 m100%

For example, the concrete structure’s weight = 125 ÷ 500 × 100% = 25%.

Swipe sideways to see every column →
The RAB Upah tab in the free template
The RAB Upah tab in the free template: each work item’s value (quantity × unit price) is the basis of its weight.

Using weights for project progress

Project progress = the sum of (weight × progress) over all work items. For example, preparation 100% done, foundations 100%, structure 60%, walls 20%, the rest not started:

Work itemWeightProgressWeight × progress
Preparation2%100%2.0%
Foundations12%100%12.0%
Concrete structure25%60%15.0%
Walls15%20%3.0%
Others46%0%0.0%
Project progress32.0%

For the S-curve, each item’s weight is spread over the weeks it runs. A 25% concrete structure built over 5 weeks plans 5% a week.

VAT, lump-sum items and addenda

How to calculate weights in Excel

  1. Make sure each work item has a value: quantity × unit price, for example in column E.
  2. Add the total below, for example =SUM(E5:E12) in cell E13.
  3. In the weight column enter =E5/$E$13 and copy it down. The $ signs keep the total cell fixed.
  4. Format the weight column as a percentage and check the total: =SUM(F5:F12) must be 100%.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is a work item weight (bobot)?

The share of a work item’s value in the whole project’s value, as a percentage. All weights add up to 100%.

What is the formula for weight?

Value of the work item divided by the total project value, times 100%. Rp125 million out of Rp500 million is 25%.

How do I work out project progress from weights?

Multiply each item’s weight by its progress and add them up. A 25% structure that is 60% done adds 15% to project progress.

Is weight calculated from quantities?

No. Weight comes from value (quantity × unit price), because quantities of different kinds of work cannot be compared.

References

  1. Permen PUPR No. 8 of 2023 (JDIH PUPR, Indonesian): where the budget values behind weights come from
  2. Ten Six: Performance % Complete in P6: cost-weighted progress