How to Make a Construction Cost Plan (RAP) and How It Differs from the Budget (RAB)

What a contractor’s cost plan (RAP) is, how it differs from the contract budget (RAB), how to build it from supplier quotes and your own crew productivity, a 15% margin example, and how to use it to control cost.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

The RAB is the price you tendered and agreed with the client. The RAP (Rencana Anggaran Pelaksanaan, the execution cost plan) is the cost you expect to actually spend to deliver that RAB. The difference is the planned profit. The RAB answers "how much we are paid", the RAP answers "how much we will spend".

1,000RAB (contract)810RAP direct cost40Site overhead150Planned margin
RAB Rp1,000 m against RAP Rp850 m: the difference is the planned margin of Rp150 m (15%).

RAB and RAP compared

RABRAP
For whomThe clientThe contractor, internal
Prices fromTender unit prices or AHSPSupplier quotes, labour-contract rates and your own crew productivity
ContentsWork items as in the contractThe same items, plus site costs not listed in the RAB
Used forContract and billingSpending limits and cost control
Shown to the clientYesNo

Example: a Rp1 billion contract

SectionRAB (contract)RAP (execution)Difference
PreliminariesRp20 mRp18 mRp2 m
FoundationsRp120 mRp100 mRp20 m
Concrete structureRp250 mRp205 mRp45 m
WallsRp150 mRp125 mRp25 m
RoofRp130 mRp105 mRp25 m
Floors and finishingRp230 mRp180 mRp50 m
Electrical and plumbingRp100 mRp77 mRp23 m
Site overhead (not in the RAB)Rp40 mminus Rp40 m
TotalRp1,000 mRp850 mRp150 m (15%)

Site overhead is the site cost that does not appear as an item in the RAB: site manager and supervisor wages, equipment hire, site office, site water and power, transport, security. In the RAB it is spread inside the unit prices; in the RAP it gets its own line so it can be controlled.

How to build the RAP

  1. Start from the agreed RAB, with the same work item codes and quantities.
  2. Re-price each item with real prices: current supplier quotes, labour-contract or subcontract rates, and your own crew’s productivity.
  3. Add a site overhead line: monthly cost times the project duration.
  4. Add a small risk allowance for items whose price is not yet certain.
  5. Work out the RAB minus RAP difference per item and in total. If the margin is too thin, or an item’s RAP is above its RAB, look for savings before work starts.
  6. Once management approves it, lock the RAP as the execution budget.

Using the RAP to control cost

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is a RAP?

Rencana Anggaran Pelaksanaan: the contractor’s planned real cost of doing the project, used as the internal spending limit.

How does the RAP differ from the RAB?

The RAB is the price agreed with the client. The RAP is the cost planned to deliver it. The difference is the planned profit.

What margin between RAB and RAP is normal?

It depends on the kind of project and its risk. What matters is working the margin out per item, so thin or losing items are visible.

Is the RAP given to the client?

No. It is an internal contractor document.