2 · ConstructionCost control / PRACTICAL GUIDE

How to Control Site Material Stock and Leftover Materials

How to record materials in and out of the site store, keep stock cards, count stock, compare actual use with the use expected from the work installed, and handle leftover materials at the end of a project.

Komander.ai Panduan team · 4 min read · Updated 9 October 2026

Materials are the largest cost on many projects, and the easiest to leak: used more than needed, damaged in storage, lent to another project, or lost. Stock control answers three questions: how much came in, how much was used, and whether that use is reasonable for the work installed.

300Opening + deliveries260Actual use230Expected40Counted balance
Cement in June (bags): actual use 260, expected 230, with a 5% allowance 241.5; a difference of 18.5 bags to explain.

The documents you need

DocumentContentsUsed for
Delivery note or goods received noteMaterial, quantity, condition, date, who received itRecording goods in and matching them to the PO
Material request slipMaterial, quantity, work item code, who asked and who approvedRecording goods out to a specific work item
Stock cardOne card per material: in, out, balanceKnowing the stock at any time
Stock count recordThe physical count of the store on a given dateChecking the stock card against reality
Transfer slipMaterial moved to another projectSo its cost moves too

Example stock card: cement (50 kg bags)

DateDetailsInOutBalance
01/06Opening stock20
03/06Delivery note SJ-118120140
05/06Slip 041, II.2 foundations4595
12/06Delivery note SJ-131160255
15/06Slip 052, III.1 ground beams and columns95160
26/06Slip 067, IV.2 plaster12040
30/06Stock count: 40 bags counted40

Comparing actual use with expected use

Actual use = opening stock + deliveries minus the counted balance: 20 + 280 minus 40 = 260 bags. Expected use = the work actually installed (from the progress measurement) × the cement coefficient: say 230 bags, plus a 5% waste allowance makes 241.5 bags.

ItemBags
Actual use260
Expected use from the work installed230
With a 5% waste allowance241.5
Difference to explain18.5 bags, about Rp1.1 m at Rp60,000 a bag

The difference can come from wasteful mixing, work that was broken out, cement that set because it was stored too long, or material taken without a slip. Go through it with the site manager every month, for the largest materials: cement, steel, blocks, tiles.

Steps for stock control

  1. Make one person responsible for the store, and keep one locked storage place.
  2. Record every delivery from the delivery note and match it to the PO: type, quantity and condition. Reject damaged goods on the spot.
  3. Every issue uses a request slip with the work item code, signed by the site manager.
  4. Update the stock card every day.
  5. Count the stock physically every week or month, on the same cut-off date as the cost report.
  6. Compare actual with expected use for the main materials, and follow up any difference beyond the allowance.
  7. Store materials properly: cement on pallets and covered, steel off the ground, oldest used first.

Leftover materials at the end

Swipe sideways to see every column →
The tab in the free cost template used for this work, with fictional example rows.
The tab in the free cost template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is a material stock card?

A record per material of every delivery, issue and the balance, so the store’s stock is known at any time.

How do I tell if materials are being wasted?

Compare actual use (opening stock + deliveries minus the balance) with expected use (installed quantity × coefficient) plus a waste allowance.

How often should stock be counted?

Every week or month, on the same cut-off date as the cost report.

How do I record leftovers moved to another project?

With a transfer slip, so their cost leaves the original project and goes to the receiving one.