House Construction Progress Reports for Banks and Buyers

How a developer reports construction progress per unit to the bank (mortgage or construction loan) and to buyers: the stage of work, percent progress, dated photos, target handover and mortgage status.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

A housing developer usually has two readers of progress reports outside its own team. The bank, when mortgage or construction loan disbursement follows construction progress. And the buyer, who wants to know when the house will be ready. Both need reports per unit, not per project, with evidence that can be checked.

C5-05100%C5-0685%C5-0762%C5-0845%C5-0915%foundationwallsroofplasterdone
Progress per unit for the bank and buyers.

What a unit report contains

ColumnExample
Block and unit numberC5-07
Type36/72
Stage of workRoof on, plastering started
Physical progress62%
Dated photos3 photos, 23/06/2026
Target handoverOctober 2026
Buyer statusMortgage signed 12/05/2026
NotesWaiting for aluminium frames

Stages of work and their weights

To keep unit progress consistent, use the same stages for every unit, with weights from the unit budget. An example for a type 36 house:

StageWeightCumulative progress when done
Foundations and ground beams15%15%
Structure and walls30%45%
Roof15%60%
Plaster, floors, frames25%85%
Finishing, power, water15%100%

Reports for the bank

Reports for buyers

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What goes into a construction progress report for the bank?

Progress per financed unit: stage of work, percent progress, dated photos and a progress certificate, in the bank’s format.

How is progress per house worked out?

Use stages of work weighted from the unit budget, then add the weights of finished stages and the part done of the current one.

How often should buyers be updated?

Regularly, for example monthly, and straight away when the target handover moves.

Why must bank progress match the internal measurement?

So it can be checked and trusted. Inflated progress can hold up the next disbursement.