Extension of Time Claims (EOT): Valid Causes, Evidence and an Example

How to claim an extension of time on a construction project: which causes qualify, when to notify, evidence from daily reports, working out the critical path impact, the contract amendment, and the late penalty avoided.

Komander.ai Panduan team · 2 min read · Updated 9 October 2026

When a project runs late for reasons outside the contractor’s control, such as added work, late site access or drawings from the client, or force majeure, the contractor can ask for more time. Without an extension approved by contract amendment, the delay still attracts the late penalty. The keys: notify on time and keep evidence.

123456789Contract 32 wkAdded workExtended 35 wkMonth
A 3-week extension for added work on the critical path (1 month = 4 weeks).

Causes that do and do not qualify

CauseClaimable?Note
Added work from the clientYesIf it adds work on the critical path
Late site access, drawings or approvals from the clientYesRecord the request date and the date received
Force majeure (disaster, government policy)Yes, as the contract saysMust be notified within the contract deadline
WeatherDepends on the contractUsually only when far beyond normal for the season
Contractor short of workers or materialsNoContractor’s risk

Steps

  1. Notify the client in writing straight after the event, within the deadline in the contract.
  2. Collect evidence: daily reports, photos, request letters, change orders, weather records.
  3. Work out the impact on the critical path, not just how long the event lasted.
  4. Submit the extension request with the calculation and evidence.
  5. Once approved, put it in a contract amendment and update the schedule and S-curve.

Worked example

ItemValue
EventCCO-02: add terraces and canopies to 12 houses, week 18
Duration of the added work3 weeks, on the critical path (before finishes)
Extension requested and approved3 weeks: from 32 to 35 weeks
Penalty avoided1/1000 × Rp1,007.65 m × 21 days = Rp21.16 m

The penalty follows the contract; in this example 1/1000 of the contract value per day. On government projects, contract changes follow Perpres 16/2018 as amended and the LKPP rules; on private projects, the contract clauses.

Common mistakes

Start from a template

The full guide is in How to create a weekly construction schedule report in Google Sheets. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

When can a contractor ask for more time?

When the delay is caused by things outside its control, such as added work, client delays or force majeure, and it was notified as the contract requires.

What evidence is needed?

Daily reports, photos, letters, change orders, and the impact on the schedule’s critical path.

Is a verbal extension enough?

No. It must be in a contract amendment so that the penalty is not charged.

References

  1. BPK Central Sulawesi: contract extensions (Indonesian): government projects