KomanderGuides
2 · ConstructionCost control / PRACTICAL GUIDE

Simple Earned Value for Construction Projects: PV, EV, AC, CPI and SPI

How to use earned value on construction projects in plain words: planned value, earned value, actual cost, the cost and schedule indices (CPI, SPI), and a forecast final cost. A week 8 example with a chart.

Komander.ai Panduan team · 3 min read · Updated 9 October 2026

A cost report shows how much money has gone out. A progress report shows how much work is done. Earned value combines them in three numbers, so you see at once whether the project is overspending and whether it is late.

010020030040050012345678PV 450EV 400AC 440
PV planned EV earned AC actual · Earned value up to week 8 (Rp million): PV planned, EV earned, AC actual cost.

The three base numbers

NumberMeaningWhere it comes from
PV (planned value)The value of work that should be done by todayS-curve planned cumulative × total budget
EV (earned value)The value of work actually doneActual progress from site measurement × total budget
AC (actual cost)The cost incurred for that workThe job cost report up to the cut-off

Example at week 8

ItemValue
Total budget (BAC)Rp1,000 m
Planned cumulative at week 845%, so PV = Rp450 m
Actual progress40%, so EV = Rp400 m
Actual cost to the cut-offAC = Rp440 m
CPI (cost index) = EV ÷ AC400 ÷ 440 = 0.91
SPI (schedule index) = EV ÷ PV400 ÷ 450 = 0.89
Forecast final cost (EAC) = BAC ÷ CPI1,000 ÷ 0.91 = Rp1,100 m
Forecast final varianceRp100 m over budget

How to read the numbers

Steps every week

  1. Use the same budget for all three numbers: the RAP for a contractor, the RAB for an owner.
  2. Take this week’s planned cumulative from the S-curve for PV.
  3. Take actual progress from the site measurement (weight × progress per item) for EV.
  4. Take actual cost to the same cut-off, including costs incurred but not yet billed, for AC.
  5. Work out CPI, SPI and EAC, and track the trend week by week. One number can be chance; a three-week trend is more reliable.
Swipe sideways to see every column →
The tab in the free cost template used for this work, with fictional example rows.
The tab in the free cost template used for this work, with fictional example rows.

Common mistakes

Start from a template

The full guide is in How to build a construction cost report that catches overruns early. It has a free template (Excel or Google Sheets) and a checker that reads your own workbook.

Get the templateCheck my workbook

Ready to use the Komander agents on your projects?

When your workbook is complete, apply for a pilot: we help connect your project data to the Finance, Cost and Scheduler agents and review the first reports with you.

Send with GmailEmail app

Send to melwani@komander.ai. Your workbook check result is included when there is one; the workbook itself is not sent.

Common questions

What is earned value?

A way to judge project cost and schedule together by comparing planned value, the value of work done, and actual cost.

What do CPI and SPI mean?

CPI = EV ÷ AC shows cost efficiency; SPI = EV ÷ PV shows speed against the schedule. Below 1 means overspending or late.

How do I forecast the final cost?

A simple way: total budget divided by CPI. Rp1,000 m ÷ 0.91 is about Rp1,100 m.

Does earned value work for small projects?

Yes. All it needs is the planned S-curve, progress measurement and weekly actual cost.